Hot rock geothermalHot rock geothermal
Heat lies a few kilometres under most places; the hard part is circulating water through dense rock at a price that pays.
Fervo's Utah plant entered commercial operation in September 2026, which Fervo calls a first for engineered reservoirs on new sites. Closed-loop and superhot routes are still at test stage in Germany and Oregon. Costs remain above the US Department of Energy's 2035 target, and induced quakes still need managing.
Rock gets hotter with depth. In the UK it warms by about 27°C per kilometre on average. Across the US, regional averages in sedimentary rock range from under 15 to over 50°C per kilometre. In most of Australia, rock hotter than 160°C lies more than 3 km down. Power plants can run on fluid above about 90°C, but hotter is far better. MIT's 2006 study assumed about 11% of heat becomes electricity at 150°C, and 22% at 350°C.
Most geothermal power today comes from natural hot-water and steam systems, called hydrothermal fields. They need hot rock plus enough natural cracks for water to flow quickly. Such fields are rare, and most generating capacity sits on plate boundaries or hot spots. Elsewhere, hot rock is too tight for water to pass. Enhanced geothermal systems (EGS) crack it with high-pressure water, then circulate water between wells. Closed-loop systems instead circulate fluid inside sealed wells, with no cracking. Superhot projects target rock above about 400°C, beyond water's critical point (374°C at 22.1 MPa).
Los Alamos National Laboratory began the first deep hot-rock trial, at Fenton Hill in New Mexico, in 1974. By March 2024, the US Department of Energy (DOE) counted at least 65 EGS projects across 21 countries. Early projects proved the idea but stalled on weak flow, high cost or earthquakes. Oil and gas methods have since cut drilling times sharply. On 30 September 2026, Fervo Energy declared commercial operation at its Cape Station plant in Utah.[1, 2, 3, 4, 5, 6, 7, 8, 9, 10]
Why it matters
- ≈0.3%
Geothermal plants made about 96–98 TWh in 2023, roughly 0.3% of world electricity, Geoscience Australia reports. Australia had no geothermal power plant running in 2025.[5]
- >75% utilisation
World geothermal capacity ran at over 75% utilisation in 2023, the International Energy Agency (IEA) says; wind ran under 30%. Utilisation, or capacity factor, is actual output divided by output at continuous full power.[4, 11]
- >13 million EJ
A 2006 MIT-led study put the heat in US rock down to 10 km at over 13 million exajoules (EJ). It judged over 200,000 EJ extractable, about 2,000 times US primary energy use in 2005.[2]
- 40 GW → 5,000+ GW
Engineered reservoirs could lift the US geothermal resource from about 40 GW to over 5,000 GW, DOE estimated in 2024. Only 3.7 GW of the 40 GW from natural fields was generating.[4]
- Up to 15% of growth
With better technology and lower costs, geothermal could supply up to 15% of world electricity demand growth to 2050. That would mean up to 800 GW of plants, the IEA estimates.[11]
What's in the way
| Bottleneck | How it's tackled now | What would change it |
|---|---|---|
| Drilling cost and speed in hard, hot rock | Drilling is the largest single cost, at 40% or more of a project, DOE says. Oil and gas methods are speeding it up. In July 2026 Fervo reported drilling a Utah well 5.9 km along the hole in 21 days. Its first horizontal well, at Project Red in Nevada in 2022, took 70 days to reach about 3.4 km. At Geretsried in Germany, Eavor reported severe vibration in deep hard rock that damaged tools and shortened bit life. | Longer-lasting bits and faster drilling in hard rock: Eavor says it tripled bit run life at Geretsried. Bit-free drilling is also being tried. Quaise reported drilling 100 m into granite in 2025 with millimetre-wave energy instead of a bit.[4, 9, 12, 13, 14] |
| Tools and electronics at high temperature | Downhole electronics were long limited to about 150°C, MIT's 2006 review said. Fluids above about 190°C can damage rubber seals. MIT said most packers, which seal off sections of a well, used rubber parts limited to about 225°C. Eavor used insulated drill pipe so standard oil and gas steering tools could work in hotter rock. | Proven high-temperature electronics, all-metal packers and long-life downhole pumps; MIT flagged all three as gaps in 2006. DOE said in 2024 that superhot wells above 400°C need tougher drilling and stimulation (crack-opening) methods, still in development.[2, 4, 13] |
| Making fractures and keeping them open | Water must spread through many cracks, not race down one shortcut. At Habanero, nearly all flow ran through one natural fault. Attempts to create a crack network at will failed. At Rosemanowes, a short circuit returned cool water too fast. At Project Red, Fervo used 16 fracturing stages with proppant, grains that hold cracks open. | Long records showing flow spread along whole wells without short circuits. In Project Red's 37-day test, output temperature kept rising, which Fervo read as no major short circuit. Utah FORGE, a DOE field laboratory, began a circulation test lasting months in August 2026.[2, 4, 8, 15, 16, 17] |
| Induced earthquakes | Pumping water in at high pressure can make faults slip. In 2006 Basel's quake of local magnitude (ML) 3.4 struck about five hours after injection stopped. DOE-funded projects must follow its seismicity protocol, which describes 'traffic light' rules. At Cape Station, Fervo pauses work for at least six hours from magnitude 2.0, and 24 hours from 3.0. From February 2024 to October 2026 it logged 167 'yellow' and three 'red' events there. | Reliable forecasts of the largest possible quake before injection starts. DOE's 2012 protocol notes that traffic lights do not cover quakes after pumping ends. Advisers to the Pohang inquiry called for better models of runaway triggered quakes.[4, 7, 18, 19, 20] |
| Water use and losses | Plants re-inject most of their water, but some is lost to the rock. DOE puts consumption by conventional and EGS plants at about 1.1–2.8 litres per kWh. At Fenton Hill, raising pressure for more flow also grew the reservoir and lost more water. Eavor says its sealed laterals (horizontal branch wells) at Geretsried lose 0.5–2% of the circulating flow. | Using non-drinking water, such as treated wastewater, which The Geysers field in California already injects. Eavor expects losses near 0.1% in deeper, tighter rock.[2, 4, 12] |
| Reservoirs cooling over time | MIT expected an EGS reservoir to cool markedly over a 20–30-year life. Geodynamics modelled a fall of about 30°C over 15 years at Habanero. Eavor expects output per lateral pair to fall from over 2 to 1.3 MWth (megawatts of heat) in five years. | Far bigger heat-exchange areas. Fenton Hill's first reservoir had about 10,000 m² of contact area, roughly 100 times too small for commercial use. MIT expected operators to drill new wells into unused rock as zones cool. Rested rock would reheat within about 100 years.[2, 8, 12] |
| Permits and lead times | In the US, geothermal projects typically take 7–10 years to develop, partly because permitting is complex. The IEA says permitting and administrative delays can push commissioning out to a decade. | DOE estimated in 2024 that permitting on US public land could shrink by up to three years. The gains would come from administrative changes, technology and centralised expertise.[4, 11] |
| The cost of the electricity | DOE put the levelised cost (lifetime cost per unit) of conventional geothermal at US$61–102/MWh in 2024. Its EGS capital cost estimate fell from US$27,800/kW in 2021 to about US$14,700/kW in 2023. On 9 November 2026 Fervo said its first 100 MW at Cape would cost about US$7,000/kW in total. It targets US$5,500/kW for its next 400 MW there. | DOE's Enhanced Geothermal Shot aims to cut EGS costs 90% by 2035, to US$45/MWh. The IEA says next-generation costs could fall 80% by 2035, to about US$50/MWh, with the right support.[4, 11, 21] |
Why not just…?
The questions people ask first. Open any of them.
Why not just drill deeper?
Deeper rock is hotter, but MIT found deep wells in hard rock costly. Drilling is already the largest cost in a geothermal project, DOE says. Eavor says current drilling technology hits a limit beyond about 9 km vertical depth. The deepest well ever drilled is about 12 km.[2, 4, 12]
Isn't this just fracking?
It borrows oil and gas tools: horizontal wells and hydraulic fracturing. The IEA says up to 80% of a geothermal project's investment draws on oil and gas skills. DOE lists differences. EGS uses fewer additives and cements wells to the surface. It works deeper, in crystalline rock, and recirculates water rather than disposing of it.[4, 11]
Can it cause earthquakes?
Yes: Basel's project set off an ML 3.4 quake in 2006, and damage claims reached about CHF 6 million. In 2017 a magnitude 5.4–5.5 quake struck near Pohang, South Korea, after EGS stimulation there. In September 2026, Cape Station's largest quakes were magnitude 3.0–3.3 by Fervo's count, 2.6–3.1 by the US Geological Survey. Fervo says shaking in nearby Milford was very weak or not felt. DOE said in 2024 that no DOE-funded project had caused quakes felt by communities.[4, 7, 19, 20, 22]
Why not use old oil and gas wells?
Sometimes: MIT noted in 2006 that hot water pumped up with oil and gas could feed binary plants. These pass the heat to a second working fluid. But DOE says US shale-type oil and gas reservoirs average 1.2–1.5 km deep. Planned EGS reservoirs sit at 2.4 km or more. EGS wells also need casing (lining pipe) cemented all the way up, unlike most oil and gas wells.[2, 4]
Does the heat run out?
Locally, yes, over decades. MIT expected an EGS reservoir to cool markedly over a 20–30-year life, then reheat within about 100 years if rested. MIT says operators can drill new wells into unused hot rock, as hydrothermal fields do. Even supplying all US primary energy would mine far less than 10% of the stored heat a year, MIT calculated.[2]
Why did Australia's Habanero trial stop?
Cooper Basin granite exceeds 280°C at 4–5 km. A 1 MWe (megawatt of electricity) pilot plant ran there for 160 days in 2013. But nearly all flow came through one natural fault, and wells were costly: Habanero 4 cost about A$50 million. Its power for nearby gas producers was judged dearer than gas-fired power. A plan to sell them heat ended when Beach Energy withdrew in November 2015.[8, 23]
Why not use the heat directly instead?
Direct use avoids a large conversion loss, Geodynamics noted. At 150°C, only about 11% of the heat becomes electricity, MIT assumed. Geodynamics judged Habanero heat could compete with gas for gas processing, while its electricity could not. Australia had 134 MWth of direct-use and heat-pump capacity in 2025, but no geothermal power.[2, 5, 8]
Can it work anywhere?
In principle, nearly: the IEA says drilling beyond 3 km opens geothermal potential in nearly all countries. But heat varies: US regional gradients in sedimentary rock run from under 15 to over 50°C per km. Eavor projects that a closed loop in typical 30°C/km rock would give 20 MWe at about 15 km depth.[2, 11, 12]
Why not drill straight into magma?
Iceland did, by accident. In 2008–09 the Iceland Deep Drilling Project's first well, IDDP-1, struck 900°C magma at 2.1 km. Its 452°C steam could have run about 35 MWe, but the well was lost after two years of tests. Reykjavík Energy's next deep well, IDDP-3, aims instead for heat of about 400°C at 4–5 km.[6, 24, 25]
Why not use closed loops and skip the fracturing?
Closed loops need no fractures, but only the well wall touches the rock. So, DOE says, planned commercial loops need about 8 km depth or more, plus hundreds of kilometres of horizontal hole. Eavor's first German loop has six lateral pairs, each about 16 km of continuous wellbore. In May 2026 it gave about 8.5 MWth. Since start-up its plant has averaged 11.8 MWth of heat at about 4.3% conversion: roughly 0.5 MW of electricity.[4, 12, 26]
Why not just copy Iceland?
Iceland sits on the Mid-Atlantic Ridge. Reykjavík Energy taps its high-temperature fields at about 2–3 km and up to 350°C. Such fields need hot rock plus natural cracks, and DOE says they are rare. Most of the world's geothermal capacity sits on plate boundaries or hot spots. Australia has no known active volcanism.[3, 4, 5, 6, 25]
If early projects failed, why should it work now?
Shale drilling matured: horizontal wells and staged fracturing make many cracks, giving more hot surface per well pair. Tougher PDC (polycrystalline diamond compact) bits, backed by DOE investment in the 1980s, raised drilling rates. DOE says drilling rates at Utah FORGE rose over 500% after its first well in 2017. In 2023 Fervo's Project Red wells flowed up to 63 L/s, equal to a peak of about 3.5 MW electric. Its Cape Station reached commercial operation in September 2026.[4, 10, 16]
Dead ends
- 1974–2000
Fenton Hill hot dry rock project (US)
Los Alamos fractured hot granite-type rock to make a reservoir at 3 km and about 200°C. A deeper one, begun in 1979, reached 4.4 km and 300°C. The project proved the idea by 1980 but never reached commercial flow at low enough pumping pressure. Higher pressure grew the reservoir and lost more water. With funding prospects very low, field work ended by 2000.[2]
- 1977 to at least 1990
Rosemanowes (UK)
Camborne School of Mines fractured Cornish granite to about 2.6 km, kept below 100°C on purpose. It was a rock-mechanics test, never meant to make power. The fractured zone grew downwards, against predictions, and a short circuit returned cool water too fast. Continuous circulation then ran for about four years from late 1986. In 1987 Europe chose to pool its hot-rock effort at Soultz, in France, instead.[2]
- 2006–2009
Deep Heat Mining Basel (Switzerland)
Engineers pumped about 11,500 m³ of water into rock 4–5 km below Basel. After a felt ML 2.6 quake, the traffic-light plan cut and then stopped injection. About five hours later an ML 3.4 quake caused minor damage and about CHF 6 million in claims. The canton ended the project in 2009 after a risk study.[7]
- 2016–2017
Pohang EGS project (South Korea)
Five high-pressure stimulations of two wells about 4.2–4.3 km deep ran from January 2016 to September 2017. In November 2017 a magnitude 5.4–5.5 quake hit Pohang, with one death and over US$75 million in direct damage. The project was suspended. A 2019 government-commissioned review found injection had triggered the quake; a 2023 paper argued it could also have been natural.[20, 22]
- 2003–2015
Habanero, Cooper Basin (Australia)
Geodynamics drilled from 2003 into granite above 280°C, 4–5 km under South Australia's Cooper Basin. One well's casing failed in 2009 from caustic stress-corrosion cracking. A 1 MWe pilot ran for 160 days in 2013, but its power could not compete with gas. A heat-supply plan lapsed in November 2015, and Geodynamics planned to plug the wells in 2016.[8, 23]
- 2008–09, then two years of tests
IDDP-1 magma well, Krafla (Iceland)
Iceland's deep drilling project aimed for supercritical fluid but hit 900°C magma at 2.1 km. The well produced 452°C steam, enough for about 35 MWe. After two years of flow tests its master valves failed. Quenching (rapidly cooling) the well collapsed its casing, so it was abandoned.[6]
Who's working on it
-
Fervo Energy (US)
EGS with horizontal wells, several drilled from each pad, using methods adapted from oil and gas. Building Cape Station in Beaver County, Utah: about 100 MW in Phase I, then 400 MW more.
First power came on 24 September 2026; the first 33 MW (net) block began commercial operation on 30 September. On 9 November Fervo said block 2 was sending test power and block 3 was being commissioned. Both are due in commercial operation by 1 January 2027. Fervo expects first power from the 400 MW phase in mid-2028.[10, 21, 27]
-
Utah FORGE (US; DOE-funded, led by the University of Utah)
A DOE field laboratory near Milford, Utah, that tests EGS drilling, fracturing and flow methods in basement rock.
It drilled two wells between October 2020 and April 2024 and created a reservoir between them. A month-long test in August 2024 injected about 26 L/s and produced water at about 188°C. In August 2026 DOE said a circulation test lasting months was starting.[4, 17, 28, 29]
-
Eavor Technologies (Canada; project in Germany)
Closed loops: two vertical wells joined by pairs of long horizontal laterals about 4.5 km down, at Geretsried in Bavaria. Designed for four loops giving 8.2 MWe or 64 MWth.
Loop 1 began delivering electricity in December 2025. In May 2026 Eavor said a cementing flaw led it to stop at six of 12 planned lateral pairs. Four pairs flowed, giving about 8.5 MWth. In October 2026 Eavor said it would withdraw both drilling rigs for now, delaying Loop 2. On 26 October the local heat company, ILN, said it would withdraw from its 2024 heat contract.[12, 26, 30, 31, 32]
-
Mazama Energy (US)
Superhot EGS at Newberry, Oregon, pushing towards rock at 400°C.
In October 2025 it reported two connected wells, with 331°C at the bottom of the hole. It then planned a 15 MW pilot for 2026. In September 2026 it raised US$135 million and said it aims to demonstrate power generation in 2027. Its second well, Athena, was then drilling towards 400°C rock.[33, 34]
-
Quaise Energy (US)
Developing millimetre-wave drilling, which removes rock with beamed energy instead of a bit. Building Project Obsidian, a 'superhot' EGS in its words, south of Bend, Oregon. DOE lists its bottom-hole temperatures as 265–365°C.
In July 2025 it reported drilling 100 m into granite in Texas with millimetre waves. In September 2026 DOE selected it for up to US$25 million, and a confirmation well was being drilled. Quaise expects first power in 2030.[14, 35, 36]
-
Reykjavík Energy and the Iceland Deep Drilling Project (Iceland)
Drilling deeper than today's 2–3 km fields, aiming for heat above 400°C at 4–5 km.
IDDP-2 reached 426°C at 4.5 km in January 2017. In October 2025 Reykjavík Energy said it was preparing IDDP-3 at Nesjavellir. Its English web page says drilling starts at the end of 2026. Its Icelandic page, read in November 2026, says the first quarter of 2027.[6, 24, 25, 37]
-
XGS Energy (US)
Sealed closed-loop wells, boosted by a heat-conducting material that XGS places in the well.
In September 2025 it reported over 3,000 hours of closed-loop running in a long-idle well at California's Coso field. The fluid came out over 70°C hotter than it went in. In September 2026 DOE listed support for its deep test (appraisal) well in Socorro County, New Mexico.[36, 38]
-
Sage Geosystems (US)
'Pressure geothermal': engineered hot-water reservoirs in hot dry rock, drawing on the rock's pressure as well as its heat.
In January 2026 it said it had raised over US$97 million. Part of the money is for its first commercial power facility, at an existing Ormat power plant. On 22 September 2026 it said it had chosen Ormat's Blue Mountain plant for its next commercial-scale EGS facility.[39, 40]
-
I-Pulse, Greenvale Mining and Sunrise Energy Metals (project in Queensland, Australia)
Plans deep wells into hot granites in Queensland's Millungera Basin, about 200 km east of Mount Isa, using pulsed-power drilling.
In March 2026 I-Pulse said it would take over running and funding the project, to earn up to 65%. Geoscience Australia counted 123 geothermal exploration tenements (permits) and applications in December 2025, and no geothermal power.[5, 41]
Sources
- Geothermal technologies
- The Future of Geothermal Energy: Impact of Enhanced Geothermal Systems (EGS) on the United States in the 21st Century (INL/EXT-06-11746)
- Australia's Energy Commodity Resources 2025: Geothermal
- Pathways to Commercial Liftoff: Next-Generation Geothermal Power
- Australia's Energy Commodity Resources 2026: Geothermal
- The Iceland Deep Drilling Project 4.5 km deep well, IDDP-2, in the seawater-recharged Reykjanes geothermal field in SW Iceland has successfully reached its supercritical target (Friðleifsson et al.), Scientific Drilling 23, 1–12
- Induzierte Erdbeben im Nachgang des eingestellten Geothermieprojekts in Basel (Induced earthquakes after the halted Basel geothermal project)
- Habanero Geothermal Project Field Development Plan
- Fervo Energy Learning Curve Continues on 3rd Generation Well Design, Boosting Drilling Rates by 143% Since Its First Cape Station Well
- Fervo Energy Declares Commercial Operation at Cape Station Ahead of Schedule, Leading the Race for Next-Generation Geothermal Energy
- The Future of Geothermal Energy: Executive summary
- Technical Update from Geretsried: What we built, what we learned, and what comes next
- Eavor's 2025 – Year In Review
- Quaise Energy Achieves Drilling Milestone with Millimeter Wave Technology
- Utah FORGE: Reports on Northwestern Nevada Well Doublet Drilling and Testing by Fervo Energy (dataset record)
- Commercial-Scale Demonstration of a First-of-a-Kind Enhanced Geothermal System (Norbeck and Latimer; preprint, not peer reviewed)
- Running Hot, Keeping Cool: FORGE Embarks on Extended Circulation Test
- Protocol for Addressing Induced Seismicity Associated with Enhanced Geothermal Systems (DOE/EE-0662)
- October 2026 Insights on Seismic Behavior at Cape Station
- Triggering of the Pohang, Korea, Earthquake (Mw 5.5) by Enhanced Geothermal System Stimulation (Ellsworth et al.), Seismological Research Letters (accepted version)
- Fervo Energy Reports Third Quarter 2026 Results
- The 2017 Pohang, South Korea, Mw 5.4 main shock was either natural or triggered, but not induced (McGarr and Majer), Geothermics 107, 102612
- Cooper Basin Enhanced Geothermal Systems (project page)
- Reykjavik Energy leads the development of supercritical geothermal utilization
- Deep geothermal utilization (English page; undated web page, read November 2026)
- Eavor Technologies Achieves First Electricity Production at Geretsried Site
- Fervo Energy Achieves First Power at Cape Station, a Landmark Moment for the Future of Enhanced Geothermal Systems
- Department of Energy Selects University of Utah Site for $140 Million Geothermal Research and Development
- FORGE
- EAVORLOOP: The Eavor-Loop first of its kind commercial scale implementation of an innovative closed-loop geothermal technology (Innovation Fund project factsheet)
- Verzögerung beim zweiten Loop (Delay to the second loop)
- ILN zieht Konsequenzen aus der aktuellen Entwicklung des Geothermieprojekts (ILN acts on the latest developments in the geothermal project)
- Mazama Energy Unveils the World's Hottest Enhanced Geothermal System, Paving the Way for Affordable Clean Power on a Global Scale
- Mazama Energy Raises $135 Million to Scale the World's Hottest Engineered Geothermal System
- Quaise Energy Selected for Up to $25 Million in U.S. Department of Energy Support to Advance World's First Commercial Superhot Geothermal Power Plant
- Pilots and Demonstrations: Next-Generation Field Tests and Drilling for New Resources
- Djúpnýting jarðhita (Deep geothermal utilisation; Icelandic page, undated web page, read November 2026)
- XGS Energy Announces 3000-Hour Operations Milestone for Water-Independent Geothermal System
- Sage Geosystems Raises Over $97 Million To Deploy World's First Commercial Pressure Geothermal Power Generation Facility
- Sage Geosystems home page, newsroom list: 'Sage Geosystems Selects Ormat's Blue Mountain Power Plant for Next Commercial-Scale EGS Facility', dated 22 September 2026 (undated web page, read November 2026)
- I-Pulse Announces Strategic Partnership to Advance Geothermal Pulsed Power Applications in the Millungera Basin, Australia